MSF for Agile Software Development Visual Studio 2005 Team System logo

Activity:

Mitigate a Risk

Participating Roles

Responsible:

Project Manager

Overview

Entry Criteria

    Dependencies:

    • A risk poses an immediate threat or results in adverse consequences to the project.

    Sub-Activities

    1

    Reduce Probability

    • Propose feasible means to reduce the probability of the adverse event.
    • Assess the cost of development and ownership of each proposal against the risk exposure. Estimate the probability and potential impact.
    • Decide if there is a cost-effective method or combination of means available to reduce the probability.

    2

    Reduce Impact

    • If the risk exposure is still too high to accept, propose feasible approaches to reduce the impact of the adverse event.
    • Assess the cost of development and cost of ownership of each proposal against the remaining risk exposure.
    • Decide if there is a cost-effective method or combination of means available to reduce the probability.

    3

    Make Contingency Plans

    • If the remaining risk exposure is still too high to accept, examine, all assumptions and quality of service requirements, especially those that involve deployment environment, availability, and accessibility.
    • If no changes can be made to the original context, develop action plans for users and support staff to handle adverse events in the best and most cost effective way.

    4

    Apply Decisions

    • Implement the selected approach to reduce the probability of occurrence and impact.
    • Close the risk work item. 

    Exit Criteria

    The risks that pose the greatest threat to the success of the project have been mitigated.