MSF for Agile Software Development Visual Studio 2005 Team System logo

Activity:

Evaluate Test Metric Thresholds

Participating Roles

Responsible:

Project Manager

Consult:

Tester

Overview

Entry Criteria

    Dependencies:

    • The test approach worksheet is completed and published.

    Sub-Activities

    1

    Review Test Reports

    • Review the test reports to understand where the project is relative to the test metric thresholds.
    • Refine the test approach worksheet to update the test metric thresholds.
    • Plan future iterations to bring the numbers into line with the thresholds.

    2

    Create Test Tasks and Risks

    • With the testers to create and assign test tasks necessary to bring testing the project on track.
    • Work with the business analyst and testers to create an understanding of any issues around functionality or bugs.
    • Create risk work items for any areas that might be at risk due to not meeting threshold targets.

    Exit Criteria

    The test approach worksheet is updated if necessary and republished.

    New test tasks or risks are created as needed.

    © 2006 Microsoft Corporation. All rights reserved.