Once the database project has been verified, it is ready to be checked in to the source code control system so that it can be leveraged by the entire team.
Entry Criteria
The database project is verified on a sandbox server and is ready to be used by developers.
Sub-Activities
1
Add Project to Source Control System
Ensure the desired source control system is appropriately configured.
Add the solution that contains the database project to source control.
2
Check In Project
Check in the project to the source control system, and associate the work item with the check-in.
3
Resolve Work Item
Resolve the task to establish a database project, and assign it to the project manager.
Exit Criteria
The database project is checked in to source control.